Chevron-Phillips
Rollcon was engaged for a rehabilitation/maintenance paving project for Chevron-Phillips. The scope requested milling the in situ asphalt pavement, stabilizing, fine-grading and proof-rolling the subgrade, and installing six-inch and eight-inch RCC pavement at a working plant site. Several critical elements included strict, comprehensive, and continuous adherence to safety, limited disruption to current operations, and a speedy turnaround time from start to full use of seven working days.